As we only have approximately 10 weeks to complete this project. We created a timeline that will help us be on track. We expect this timeline to change as we move forward and come across different challenges.

Timeline:
Week 1- Conceptualize engineering design for our product and make a budget and begin research of coding for the Automated Transport Car (ATC) and begin proposal
Week 3- Continue construction of ATC and start coding for motion sensors and submit proposal
Week 4- Continue to code ATC by making it track a line using the light sensor
Week 5- Still work on making the ATC track a line successfully,start to incorporate other sensors onto the ANC, and begin the draft of final paper
Week 6- Fix any tweaks that we have bumped into using incorporating other sensors into ATC and switch the programming software from RobotC to BricxCC
Week 7- We will continue to work on the final paper while working on the ATC
Week 8- Work on the ATC and final paper
Week 9- Finalize any problems with the ATC and the final paper and presentation while practicing the presentation.
Week 10-Hand in our final paper and present our ATC to the class.